1. Explain
the different methods of building estimates
2. Explain the following general items of work involved in the estimation
for a building along with the process of calculations.
(a) Earthwork in excavation.
(b) Earthwork in filling.
(c) Brick at soling.
(d) Cement concrete in foundation.
(e) Masonry work
(f) Damp proof course.
(g) White washing
(h) Painting
3. Prepare a detailed estimate
for earthwork for a portion of a road from the following data
Distance in m RL of ground RL of the formation
0 73.12
72.42
60 72.44
120 71.86
180 72.08
240 71.30 Downward
gradient 0.8% up to 240 m
300 70.80
360 70.54
420 70.82
480 70.96
540 71.50 Upward
gradient 0.5%
Proposed Formation width of road is 10m,
side slopes are 2:1 in banking and 1 1/2 :1 in cutting. Draw
L-section and cross sections.
4. Prepare Rate analysis for the following
items
(a) I-class Brick work in super structure with 20cm x 10cm x 10cm with
cement sand mortar 1:6
(b) Cement concrete 1:2:4 with Stone Ballast
5. Estimate the quantities of the following
items of a residential building from the drawing given below by Long wall Short
wall method
(i)
Earthwork in excavation in foundation
(ii)
Lime Concrete in foundation
(iii)
First class brickwork in cement sand mortar in foundation and plinth
(iv)
2.5cm damp proof course
(v)
First class brick work in lime mortar in super structure